The Federal Ministry of Defence (BMVg) is strengthening its commitment to renewable energy.
At its Berlin headquarters, a new 380 kWp photovoltaic system is being developed with FuturaSun’s Silk Orange modules, in collaboration with the VODASUN® Group (Munich).
The system is scheduled to go into operation in November 2025.
Installed on a listed historic building in the center of Berlin, the project represents one of the largest colored photovoltaic systems in Germany.
Across an area of 2,000 m², more than 900 high-efficiency Silk Orange modules have been installed, each delivering 400 Wp of power, and all connected through SMA inverters.
The system is designed to generate clean electricity while maintaining the architectural integrity of the site.
With its orange-brown color finish, the installation integrates seamlessly with the existing façade, combining technical performance with aesthetic compatibility.
Performance and sustainability
Once operational, the system will produce renewable energy capable of reducing annual CO₂ emissions by approximately 211 tons.
This contribution supports the Ministry’s broader goals of energy efficiency, operational resilience, and supply security.
“The Federal Ministry of Defence demonstrates that climate protection and national security can go hand in hand. Investing in solar energy is another step toward a modern, resource-efficient, and independent energy supply,”
explains Jakob Katzendobler, CEO of the VODASUN® Group.
Design integration
The Silk Nova Orange modules were selected for their visual harmony and proven reliability.
Their warm terracotta tone allows the installation to blend with the historic context while delivering the performance of modern photovoltaic technology.
Project Details
| Location | Berlin, Germany |
| Client | Federal Ministry of Defence (BMVg) |
| Partner | VODASUN® Group |
| Module type | FuturaSun FU400M Silk Nova Orange |
| Module technology | Monocrystalline N-Type half-cell |
| Module output | 400 Wp each |
| Total capacity | ~380 kWp |
| Inverters | SMA Solar Technology |
| Installation area | ~2,000 m² |
| Commissioning | November 2025 |
| CO₂ reduction | ~211 tons/year |